Cost estimation

also: Cost estimate, Cost estimating

Definition

Cost estimation quantifies the financial resources a project is likely to need. It covers staff costs based on the estimated effort, non-staff costs, materials, external services, travel costs, overhead surcharges and reserves for risks. It becomes more accurate as planning progresses; many organizations specify which level of accuracy is expected in which phase.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Cost estimation

Distinction

The cost estimate is the result of a calculation; the budget is the approved amount. Cost planning distributes the estimated costs over time and across cost centres. A quotation (Kostenvoranschlag) is an estimate that a contractor submits to its client; it can acquire legal significance if it is substantially exceeded.

In practice

A district council is planning a new ambulance station. In the feasibility study, a rough estimate based on benchmark rates is produced with a range of minus twenty to plus thirty per cent. After the design stage, a detailed calculation by building element follows, with an accuracy of around ten per cent. Only on this basis does the district apply for grant funding and take the decision to build.

Frequently asked questions

How accurate does a cost estimate need to be?

That depends on the phase. Early on, ranges of thirty per cent and more are common; before implementation, the estimate should be considerably narrower.

Which stages of cost determination exist in construction?

DIN 276 distinguishes several stages that become more accurate as planning progresses, from the cost framework (Kostenrahmen) through the cost estimate (Kostenschätzung) and cost calculation (Kostenberechnung) to the final cost statement (Kostenfeststellung) after completion.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Cost estimation. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-estimation/

Short form

Hain, D. (n.d.): Cost estimation. PMDecoder. https://pmdecoder.com/en/glossary/cost-estimation/ (retrieved 24 November 2026)

BibTeX
@misc{costestimation,
  author  = {Hain, Dennis},
  title   = {Cost estimation},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/cost-estimation/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/cost-estimation/">
  <p>Determining the expected costs of a project or its parts on the basis of scope, prices and assumptions</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-estimation/">Cost estimation</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.