Empiricism
also: Empirical process control
Definition
Empiricism is the theoretical foundation of Scrum. It holds that we learn through experience and should base decisions on what has actually been observed. Scrum combines this approach with lean thinking, which avoids waste and keeps attention on what matters. Empiricism rests on three pillars. Transparency makes the work and the way it is done visible to everyone involved. Inspection means looking at artifacts and progress regularly and thoroughly so that deviations are spotted early. Adaptation means changing the approach or the result quickly as soon as something falls outside acceptable limits. The three pillars build on one another: without transparency, inspection is misleading; without adaptation, it has no consequences.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
Plan-driven approaches aim to predict an undertaking as completely as possible at the outset. Empirical working assumes that in complex environments much only becomes clear along the way, and therefore plans in short steps with frequent checks. The term shares its orientation towards observation with empiricism in the scientific sense, but it does not refer to a research methodology. The PDCA cycle is based on a related idea.
In practice
At the start, a team estimates that moving an online form to a new platform will take four Sprints. After the first Sprint, the Sprint Review shows that far fewer people abandon the new form, but that migrating old data takes twice as much effort as expected. Instead of sticking to the original plan, the Product Owner reorders the Product Backlog and postpones the data migration until a simpler procedure has been tried out.
Frequently asked questions
Why does Scrum rely on empiricism rather than detailed plans?
Scrum is intended for complex work whose course cannot be predicted. In such settings, what has already happened is the most reliable basis, and the regular inspections build on it.
Which events serve inspection and adaptation?
All four events within the Sprint: Sprint Planning, Daily Scrum, Sprint Review and Sprint Retrospective. The Sprint itself provides their time frame.
Source and context
- Reference
- Scrum Guide 2020, Abschnitt Scrum-Theorie
- Edition
- Scrum Guide 2020
- Author
- Dennis Hain
Differences from other editions
- Scrum Guide 2017
- Scrum rested solely on empirical process control, with transparency, inspection and adaptation as its pillars. The guide has named lean thinking as a second foundation only since 2020.
Cite this entry
Hain, D. (n.d.). Empiricism. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/empiricism/
Hain, D. (n.d.): Empiricism. PMDecoder, entry on Scrum Guide 2020, Abschnitt Scrum-Theorie. https://pmdecoder.com/en/glossary/empiricism/ (retrieved 24 November 2026)
@misc{empiricism,
author = {Hain, Dennis},
title = {Empiricism},
note = {PMDecoder, Scrum Guide 2020, Abschnitt Scrum-Theorie},
url = {https://pmdecoder.com/en/glossary/empiricism/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/empiricism/"> <p>Core principle of Scrum: insight is gained through experience, and decisions rest on observation, supported by transparency, inspection and adaptation</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/empiricism/">Empiricism</a>, PMDecoder, Scrum Guide 2020, Abschnitt Scrum-Theorie</footer> </blockquote>
Found a mistake? Let us know, we check every report.