Managing Layer

Definition

In PM², the Managing Layer takes care of the ongoing project activities. It organizes, monitors and controls the work through which the deliverables are produced and introduced into the organization, and it reports to the Directing Layer. It comprises the Project Manager on the Provider Side and the Business Manager on the Requestor Side. The two work closely together and form the hinge between the decisions of the upper layers and the performing work.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

In German the Managing Layer is called Verwaltungsebene, which has nothing to do with administration in the sense of clerical work. The Directing Layer above it sets direction and resources, while the Performing Layer below it produces the results and puts them into practice.

In practice

In a project for a new applicant management system, the Project Manager and the Business Manager plan the week every Monday: he assigns the tasks within the core team, and she clarifies open business questions with the HR department. Together they prepare the monthly report for the Directing Layer.

Frequently asked questions

Which roles belong to the Managing Layer?

The Project Manager and the Business Manager.

Why are both roles on the same layer?

Because a result only delivers benefits if delivery and implementation are managed together. Placing both roles on an equal footing is meant to secure close cooperation between the two sides.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 4.2
Edition
PM² Guide 3.1
Cite this entry
APA

Managing Layer. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/managing-layer/

Short form

Managing Layer (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.2. https://pmdecoder.com/en/glossary/managing-layer/ (retrieved 24 November 2026)

BibTeX
@misc{managinglayer,
  title   = {Managing Layer},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2},
  url     = {https://pmdecoder.com/en/glossary/managing-layer/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/managing-layer/">
  <p>Layer of the PM² project organization with Project Manager and Business Manager that organizes, monitors and controls the ongoing work</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/managing-layer/">Managing Layer</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2</footer>
</blockquote>

Found a mistake? Let us know, we check every report.