Business Governing Layer

Definition

The Business Governing Layer is the highest of the layers PM² uses to describe the organization around a project. This is where the organization defines its mission and strategy, sets priorities, decides on investments and allocates resources. It is formed by one or more senior management bodies, which act as the Appropriate Governance Body for a project. The Business Governing Layer is not part of the project team; the project reports to it via the Steering Layer.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The Steering Layer gives direction to an individual project, whereas the Business Governing Layer decides on the project portfolio as a whole. The name has nothing to do with company management in the sense of corporate law; it refers to any management level that decides on projects and funds.

In practice

At a university, the executive board together with the chancellor forms the Business Governing Layer. Every year it decides which digitalization projects are funded and provides a budget for three projects. The individual projects are then steered by their own committees, which report to the executive board every six months.

Frequently asked questions

How many layers does the PM² project organization have?

The guide describes the Business Governing, Steering, Directing, Managing and Performing Layers and adds a Support Layer for cross-cutting services.

Does the Business Governing Layer intervene in ongoing projects?

Only on fundamental questions, for example when a project deviates significantly from the approved Business Case or is to be stopped.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 4.2
Edition
PM² Guide 3.1
Cite this entry
APA

Business Governing Layer. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/business-governing-layer/

Short form

Business Governing Layer (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.2. https://pmdecoder.com/en/glossary/business-governing-layer/ (retrieved 24 November 2026)

BibTeX
@misc{businessgoverninglayer,
  title   = {Business Governing Layer},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2},
  url     = {https://pmdecoder.com/en/glossary/business-governing-layer/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/business-governing-layer/">
  <p>Top layer of the PM² project organization, at which the organization sets strategy, priorities and investments</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/business-governing-layer/">Business Governing Layer</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2</footer>
</blockquote>

Found a mistake? Let us know, we check every report.