Performing Layer

Definition

In PM², the actual project work takes place on the Performing Layer. The Project Core Team produces the deliverables, and the Business Implementation Group prepares their introduction and implements the organizational changes. Both report to the Managing Layer: the core team to the Project Manager and the Business Implementation Group to the Business Manager. Together with the Directing and Managing Layers, the Performing Layer forms the single project team on whose cooperation success depends. Its members contribute the expert knowledge without which neither usable results nor a successful introduction can come about.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Distinction

The Performing Layer (Ausführungsebene in German) must not be confused with the Executing Phase: the layer describes who does the work, the phase describes when in the life cycle the deliverables are produced. Cross-cutting services such as the Project Support Office or quality assurance belong to the Support Layer.

In practice

When a citizens' service hotline is set up, two specialists on the Performing Layer develop the knowledge base, a technician sets up the telephone system, and a team of three staff members from the citizens' office writes the call guidelines and trains the future service agents.

Frequently asked questions

Which roles belong to the Performing Layer?

The Project Core Team and the Business Implementation Group, which also includes the User Representatives.

Does the Performing Layer only work in the Executing Phase?

No. Its members already contribute to scope, estimates and plans, but they are most in demand during the Executing Phase.

Source and context

Reference
PM²-Leitfaden 3.1, Abschnitt 4.2
Edition
PM² Guide 3.1
Cite this entry
APA

Performing Layer. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/performing-layer/

Short form

Performing Layer (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.2. https://pmdecoder.com/en/glossary/performing-layer/ (retrieved 24 November 2026)

BibTeX
@misc{performinglayer,
  title   = {Performing Layer},
  note    = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2},
  url     = {https://pmdecoder.com/en/glossary/performing-layer/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/performing-layer/">
  <p>Layer of the PM² project organization with Project Core Team and Business Implementation Group that produces the deliverables and puts them into practice</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/performing-layer/">Performing Layer</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.2</footer>
</blockquote>

Found a mistake? Let us know, we check every report.