Multi-project management

Definition

Multi-project management looks at an organization's ongoing projects together. It aligns dates and resources between the undertakings, sets priorities in the event of conflicts, ensures consistent methods and reports and provides an overview of the overall status. It is often supported by a project management office. In Germany, the DIN 69909 series of standards covers the subject.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Multi-project management

Distinction

Portfolio management decides which projects are started; multi-project management ensures that the selected ones run well side by side. Programme management directs projects that are related in content, whereas multi-project management also covers independent projects that merely compete for the same resources. In common usage, the term is sometimes used as an umbrella term for all three levels.

In practice

An engineering firm with sixty employees works on around thirty projects at the same time. Each project manager plans independently, and the same specialists are repeatedly booked several times over. The firm introduces a weekly multi-project meeting: bottlenecks become visible on a shared overview, and the management decides according to agreed criteria which project takes priority in the event of conflicts.

Frequently asked questions

Which problems does multi-project management solve?

Above all, resource conflicts, contradictory priorities, a lack of overview of all undertakings and inconsistent reporting.

Does multi-project management need dedicated software?

Beyond a certain number of projects, it makes the work considerably easier. More important, however, are clear rules on who sets priorities and how requirements are reported.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Multi-project management. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/multi-project-management/

Short form

Hain, D. (n.d.): Multi-project management. PMDecoder. https://pmdecoder.com/en/glossary/multi-project-management/ (retrieved 24 November 2026)

BibTeX
@misc{multiprojectmanagement,
  author  = {Hain, Dennis},
  title   = {Multi-project management},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/multi-project-management/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/multi-project-management/">
  <p>Overarching planning and control of several concurrent projects in an organization, especially of their shared resources</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/multi-project-management/">Multi-project management</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.