Control limit

also: Action limit

Definition

Control limits are determined from the data of a stable process and usually lie three standard deviations above and below the mean. A value outside this range is very unlikely in an undisturbed process and is therefore a signal to look for a special cause and to intervene if necessary. Some control charts also contain narrower warning limits that call for increased attention.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Control limit
Topic area
Quality

Distinction

The specification limit comes from outside, from the requirements; the control limit comes from the process itself. Warning limits lie inside the control limits and do not yet lead to intervention. A fixed limit value, such as a statutory maximum, is also a requirement and not a statistical control limit.

In practice

In a validation project, a laboratory monitors the temperature of an incubator. From two weeks of measurement data it calculates a centre line of 37.0 degrees and control limits of 36.6 and 37.4 degrees. When 37.5 degrees is measured one morning, the incubator is checked immediately. The cause is a door that no longer closes properly after cleaning. Without the control limit, the deviation would only have been noticed at the prescribed upper limit.

Frequently asked questions

Why three standard deviations?

Because in a stable process a value then only very rarely falls outside by chance, so false alarms are rare, while real changes are usually noticed quickly.

When do control limits have to be recalculated?

When the process has been changed deliberately, for example through new machines or methods, and a new stable state has been established.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Control limit. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/control-limit/

Short form

Hain, D. (n.d.): Control limit. PMDecoder. https://pmdecoder.com/en/glossary/control-limit/ (retrieved 24 November 2026)

BibTeX
@misc{controllimit,
  author  = {Hain, Dennis},
  title   = {Control limit},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/control-limit/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/control-limit/">
  <p>Limit on a control chart, calculated from the natural variation of a process, whose violation triggers an investigation</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/control-limit/">Control limit</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.