Checkpoint Report or Project Progress Report?

partially overlapping

Like the other reports, the Checkpoint Report states progress. It covers only one work package, however, and goes from the Team Manager to the Project Manager.

Comparison of Checkpoint Report and Project Progress Report
PRINCE2Checkpoint ReportPM²Project Progress Report
What it coversPRINCE2 progress report from a Team Manager to the Project Manager on the status of a work package, produced at agreed intervals.PM² report from the Project Manager to the Project Steering Committee on project status compared with the baselines and the Project Charter
Equivalent in ISO 21506Progress report partially overlappingProgress report closely related