Request for quotation

also: Request for quote · abbr. RFQ

Definition

A request for quotation (Angebotsanfrage) is addressed to suppliers when it is clear exactly what is to be procured. It states items, quantities, specifications, delivery dates and place of delivery and asks for prices, delivery times and terms. Because the work is specified, the quotations can be compared mainly on price and delivery terms.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Request for quotation

Distinction

A request for proposal expects a solution of the supplier's own; a request for quotation expects only a price quotation for specified work. A request for information, by contrast, serves to explore the market without an immediate intention to buy. Legally, a request for quotation is not yet an offer but an invitation to submit one.

In practice

For a trade fair, a company needs 2,000 printed cloth bags in a specified colour and size. Purchasing sends a request for quotation with the print template, quantity and latest delivery date to four promotional products dealers. Three reply within a week. The cheapest quotation would deliver only shortly before the fair, so purchasing chooses the second-cheapest, which leaves two weeks in hand.

Frequently asked questions

When is a request for quotation sufficient?

When the work is fully described and the suppliers differ mainly in price, delivery time and terms.

How many suppliers should be asked?

Three to five is usual, to obtain a meaningful comparison without creating unnecessary effort. Internal guidelines often prescribe minimum numbers.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Request for quotation. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/request-for-quotation/

Short form

Hain, D. (n.d.): Request for quotation. PMDecoder. https://pmdecoder.com/en/glossary/request-for-quotation/ (retrieved 24 November 2026)

BibTeX
@misc{requestforquotation,
  author  = {Hain, Dennis},
  title   = {Request for quotation},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/request-for-quotation/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/request-for-quotation/">
  <p>Request to suppliers for price and delivery terms for precisely specified goods or work</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/request-for-quotation/">Request for quotation</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.