Process capability

Definition

Process capability compares the natural variation of a process with the room that the requirements allow. Two indices are common: Cp relates the tolerance, i.e. the distance between the upper and lower specification limits, to six times the standard deviation of the process. Cpk also takes the position of the mean into account and considers only the distance to the nearer limit, divided by three times the standard deviation. A value of 1 means that the variation just fills the tolerance; many industries require considerably higher values, often at least 1.33. A meaningful calculation presupposes a process in statistical control and a sufficient number of measurements.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Process capability
Topic area
Quality

Distinction

The control chart shows whether a process is stable, process capability whether it meets the requirements; a process can be stable and still not capable. If Cp is well above Cpk, the process is precise enough in itself but not centred. Machine capability considers only a single machine under short-term, largely constant conditions. When long-term data including all influences are evaluated, the terms process performance and the indices Pp and Ppk are often used.

In practice

For a vehicle project, a supplier has to drill holes with a diameter of 8.00 millimetres and a tolerance of 0.03 millimetres in either direction. After the start of series production, the project team evaluates 125 measurements: the standard deviation is 0.006 millimetres, which gives a Cp of 1.67. The mean, however, is 8.012 millimetres, so Cpk only reaches 1.0. Instead of investing in a more precise machine, the team corrects the tool setting. Cpk then rises to 1.5, and the customer approves series supply.

Frequently asked questions

Why is a high Cp value not sufficient on its own?

Because Cp only assesses the width of the variation. If the process is shifted towards one limit, defective parts are produced despite low variation. Only Cpk shows how much margin remains to the critical limit.

Can the capability of an unstable process be calculated?

Arithmetically yes, but it is not meaningful. As long as special causes are at work, the data do not allow any prediction of how the process will vary in future. The process is stabilized first and then assessed.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Process capability. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/process-capability/

Short form

Hain, D. (n.d.): Process capability. PMDecoder. https://pmdecoder.com/en/glossary/process-capability/ (retrieved 24 November 2026)

BibTeX
@misc{processcapability,
  author  = {Hain, Dennis},
  title   = {Process capability},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/process-capability/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/process-capability/">
  <p>Measure of whether a stable process produces results with so little variation that they reliably fall within the specification limits.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/process-capability/">Process capability</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.