Strategic alignment
Definition
Strategic alignment is not a one-off decision but the result of ongoing work in portfolio management. New undertakings are selected according to whether they contribute to the strategic objectives; ongoing undertakings are adjusted, put on hold or stopped when strategy or circumstances change. Good alignment shows in the fact that for every portfolio component it can be stated which objective it supports, and that no important objective is left without undertakings.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Strategic alignment
- Topic area
- Portfolios and programmes
Distinction
The strategy sets out what an organization wants to achieve; strategic alignment describes how well its portfolio fits that strategy. The business case justifies a single undertaking, usually also by its strategic contribution. Prioritization ranks undertakings, and strategic alignment is the yardstick for that ranking.
In practice
A retailer wants to generate half of its revenue online by 2028. An analysis of its portfolio shows that only eight of 31 undertakings support this objective, while twelve branch modernizations tie up most of the budget. Management puts four modernizations on hold, adds two undertakings for online retail logistics and from now on checks alignment at every quarterly review.
Frequently asked questions
How is strategic alignment measured?
For example, by assigning each portfolio component to the strategic objectives and assessing its contribution. It is revealing to see how much budget and capacity go to each objective and whether important objectives are under-resourced.
Can a well-executed project be poorly aligned?
Yes. A project can meet its schedule, cost and quality targets and still contribute nothing to the organization's objectives. This is exactly what strategic alignment in the portfolio is meant to prevent.
Source and context
- Reference
- ISO 21506:2024, 3.87
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Strategic alignment. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/strategic-alignment/
Hain, D. (n.d.): Strategic alignment. PMDecoder, entry on ISO 21506:2024, 3.87. https://pmdecoder.com/en/glossary/strategic-alignment/ (retrieved 24 November 2026)
@misc{strategicalignment,
author = {Hain, Dennis},
title = {Strategic alignment},
note = {PMDecoder, ISO 21506:2024, 3.87},
url = {https://pmdecoder.com/en/glossary/strategic-alignment/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/strategic-alignment/"> <p>State in which the undertakings in a portfolio, through selection and ongoing adjustment, actually serve an organization's strategy.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/strategic-alignment/">Strategic alignment</a>, PMDecoder, ISO 21506:2024, 3.87</footer> </blockquote>
Found a mistake? Let us know, we check every report.