Delphi technique

also: Delphi method

Definition

In the Delphi technique, selected experts answer questions independently of one another, for example on effort, risks or future developments. A facilitator evaluates the answers and feeds the summarized results back to everyone anonymously, often together with the reasons for divergent assessments. In further rounds, the participants can reconsider their judgement. The process ends when the answers have converged sufficiently or no new arguments are being added.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Delphi technique

Distinction

Unlike brainstorming, the aim is not as many ideas as possible, but a robust shared assessment. Anonymity distinguishes the method from a group discussion, in which hierarchy and persuasiveness shape the result. Wideband Delphi combines the anonymous rounds with short discussions; Planning Poker from the agile world follows a similar idea.

In practice

An insurer wants to estimate how much effort it will take to move its premium calculators to a new platform. Six experts from development, the business side and operations estimate independently of one another. In the first round, the values range from 400 to 1,500 person-days. The feedback shows that the high estimates include data migration and the low ones do not. In the third round, all estimates lie between 900 and 1,100 person-days, and the scope is described more clearly than before.

Frequently asked questions

How many rounds does the Delphi technique need?

In projects, usually two to three. Further rounds rarely bring new insights and tire the participants.

What is the method suitable for in a project?

For estimates without reliable comparative data, for assessing risks and for questions on which experts are deliberately meant to judge without being influenced.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Delphi technique. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/delphi-technique/

Short form

Hain, D. (n.d.): Delphi technique. PMDecoder. https://pmdecoder.com/en/glossary/delphi-technique/ (retrieved 24 November 2026)

BibTeX
@misc{delphitechnique,
  author  = {Hain, Dennis},
  title   = {Delphi technique},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/delphi-technique/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/delphi-technique/">
  <p>Structured survey method in which experts give assessments in several anonymous rounds and gradually bring them closer together</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/delphi-technique/">Delphi technique</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.