Brainstorming

Definition

In brainstorming, participants spontaneously put forward ideas on a clearly worded question. The ground rules are: no criticism during the collection phase, quantity over quality, unusual ideas are welcome, and others' ideas may be taken up and developed further. Only in a second phase are the contributions sorted, evaluated and selected. The method goes back to the advertising executive Alex F. Osborn.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Brainstorming

Distinction

In brainwriting, participants first write down their ideas silently, for example with the 6-3-5 method; this reduces the influence of dominant individuals. The Delphi technique collects expert judgements anonymously over several rounds and aims at assessments rather than new ideas. In project management, brainstorming is often used to search for risks and solutions or to draft a first project structure.

In practice

At the start of a project for a new visitor guidance system at a zoo, the team collects more than a hundred possible risks on cards within half an hour, from vandalism and dazzling sunlight on displays to a lack of accessibility. Criticism is explicitly forbidden in this phase. The cards are then grouped, duplicates are removed and the twenty most important risks are taken forward. Several of them would not have been mentioned by anyone in one-to-one conversations.

Frequently asked questions

How large should a brainstorming group be?

About five to twelve people from different areas has proved effective. In larger groups, quieter participants often hardly get a word in.

Why does brainstorming sometimes produce little?

Often because of a question that is too vague, premature criticism or inhibiting hierarchies. Writing ideas down silently before the exchange helps.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Brainstorming. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/brainstorming/

Short form

Hain, D. (n.d.): Brainstorming. PMDecoder. https://pmdecoder.com/en/glossary/brainstorming/ (retrieved 24 November 2026)

BibTeX
@misc{brainstorming,
  author  = {Hain, Dennis},
  title   = {Brainstorming},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/brainstorming/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/brainstorming/">
  <p>Creativity technique in which a group collects as many ideas as possible on a question in a short time without evaluating them straight away</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/brainstorming/">Brainstorming</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.