Cost trend analysis
Definition
In cost trend analysis, the current forecast of total cost is recorded at each reporting date and entered in a chart. The resulting line shows whether the expected costs remain stable, rise or fall, and it reveals creeping cost increases long before the budget is actually exceeded. It is often kept for the project as a whole and, in addition, for large work packages or trades.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Cost trend analysis
- Topic area
- Cost and economic viability
Distinction
Milestone trend analysis tracks expected dates, cost trend analysis expected costs; both use the same principle. A plan-versus-actual comparison looks at costs already incurred, cost trend analysis at the expectation for the end of the project. The cost performance indices of earned value management provide a computational basis for such forecasts.
In practice
For the construction of a new fire station, the project controllers report the forecast total cost every month. The line rises by one to two per cent five months in a row, and each individual report looks unremarkable. In the chart, however, the trend is clear. The building committee demands a root cause analysis, which shows higher prices for building services and late requests from the users, and it imposes a change freeze on the users.
Frequently asked questions
How often should the cost forecast be collected?
In line with the reporting cycle, usually monthly. A consistent method is important so that the values can be compared.
What does a falling line indicate?
That the expected costs are decreasing, for example because contracts were awarded at favourable prices. It is worth checking whether some costs have simply not been recorded yet.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Cost trend analysis. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-trend-analysis/
Hain, D. (n.d.): Cost trend analysis. PMDecoder. https://pmdecoder.com/en/glossary/cost-trend-analysis/ (retrieved 24 November 2026)
@misc{costtrendanalysis,
author = {Hain, Dennis},
title = {Cost trend analysis},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/cost-trend-analysis/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/cost-trend-analysis/"> <p>Tracking the forecast total cost of a project across several reporting dates in order to detect cost developments early</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-trend-analysis/">Cost trend analysis</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.