Change Authority or Change control board?

closely related

Like a change control board, the Change Authority decides on requests for change. In PRINCE2 it may be one person, with limited powers from the Project Board.

Comparison of Change Authority and Change control board
PRINCE2Change AuthorityPMI / PMBOK GuideChange control board
What it coversPRINCE2 role to which the Project Board delegates decisions on requests for change and off-specifications within defined limits.Body with a formal mandate that weighs up change requests and decides whether to approve, postpone or turn them down.
Equivalent in cross-frameworkChange control board closely relatedChange control board equivalent
To the term pageChange AuthorityChange control board