Task order
Definition
A task order specifies what a framework contract only regulates in general terms. The framework contract sets out types of service, prices and conditions for a period of time; with a task order, the client orders a particular service from it with its scope, deadline, deliverable and budget. For the contractor it is the basis for starting and invoicing work, and for the project it is a separate, manageable contractual item with clear boundaries.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Task order
- Topic area
- Contracts and procurement
Distinction
A framework contract creates the conditions but usually does not yet commit anyone to a particular service; only the task order does that. A contract amendment changes an existing contract, whereas a task order uses it without changing it. A work package is a planning unit within the project and may, but need not, correspond to a task order.
In practice
A state authority has a four-year framework contract with an IT service provider for software development at fixed daily rates. To connect a new online form, it issues a task order for 60 person-days with a statement of work, acceptance criteria and completion by the end of June. When it turns out that an interface to the document management system is also needed, a second task order follows instead of extending the first one.
Frequently asked questions
Does every task order have to be put out to tender again?
As a rule no, since avoiding that is the purpose of a framework contract that has already been awarded. In the public sector, however, the procurement limits of the framework contract, for example on volume, must be observed.
How are task orders controlled within the project?
Each task order has its own budget and deadlines. If they are set up as work packages or control accounts, progress and cost can be tracked for each order.
Source and context
- Reference
- ISO 21506:2024, 3.88
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Task order. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/task-order/
Hain, D. (n.d.): Task order. PMDecoder, entry on ISO 21506:2024, 3.88. https://pmdecoder.com/en/glossary/task-order/ (retrieved 24 November 2026)
@misc{taskorder,
author = {Hain, Dennis},
title = {Task order},
note = {PMDecoder, ISO 21506:2024, 3.88},
url = {https://pmdecoder.com/en/glossary/task-order/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/task-order/"> <p>Document by which specific services are actually ordered on the basis of a contract that is already in place.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/task-order/">Task order</a>, PMDecoder, ISO 21506:2024, 3.88</footer> </blockquote>
Found a mistake? Let us know, we check every report.