Retention money

also: Retainage

Definition

Retention money protects the client against remaining work being left undone or defects not being remedied. It is common to withhold a fixed percentage of each interim payment or of the final payment until a milestone is reached, acceptance has taken place or a warranty period has expired. The amount, duration and options for replacing the retention are set out in the contract.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Retention money

Distinction

With retention, money is held back; a guarantee secures the same claim through a bank or insurer, so that the contractor receives the amount immediately. In construction, a distinction is made between security for contract performance and security for claims for defects after acceptance. A contractual penalty sanctions breaches of duty, whereas retention is only a security that is paid out if the work is performed properly.

In practice

A developer agrees with the general contractor for an office building on retention of five per cent on all interim invoices until acceptance and then three per cent of the final invoice for the warranty period. The general contractor replaces the second retention with a bank guarantee in order to remain liquid. When, two years later, a defect in the ventilation is not remedied, the developer calls on the guarantee.

Frequently asked questions

How high is retention money usually?

That depends on the industry and the contract. Single-digit percentages of the contract sum are common; limits may result from contract conditions or legal provisions.

Can retention money be replaced?

Often yes, for example by a guarantee. Whether and how should be stated explicitly in the contract.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Retention money. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/retention-money/

Short form

Hain, D. (n.d.): Retention money. PMDecoder. https://pmdecoder.com/en/glossary/retention-money/ (retrieved 24 November 2026)

BibTeX
@misc{retentionmoney,
  author  = {Hain, Dennis},
  title   = {Retention money},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/retention-money/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/retention-money/">
  <p>Part of a payment due that the client withholds until certain conditions are met, as security for performance in line with the contract</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/retention-money/">Retention money</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.