Contract claim
Definition
A claim arises when a party considers that, owing to changed circumstances, it is entitled to more than originally agreed. Typical causes are change requests, lack of cooperation by the other side, late provision of items to be supplied by the client, design errors or disruptions. Claims are documented, substantiated, quantified and negotiated between the parties; if no agreement is reached, conciliation, arbitration or court proceedings follow.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Contract claim
- Topic area
- Contracts and procurement
Distinction
A change request asks for a change before it is implemented; a claim asserts entitlements arising from circumstances that have already occurred. In German construction, the usual term is Nachtrag. Claim management refers to the systematic handling of such demands, both in enforcing one's own and in defending against those of others.
In practice
On a tunnel project, the contractor encounters much harder rock than described in the geotechnical report. It documents the findings every day with photos, core samples and tunnelling rates and gives written notice of the disruption. After three months, it submits a claim for additional costs and a six-week extension of time. Because the documentation is complete, the parties reach agreement in two rounds of negotiation.
Frequently asked questions
What does a successful claim need?
Timely notice, complete documentation of cause and effect, and a traceable calculation of additional costs and time required.
How can claims be avoided?
Through clear statements of work, binding change procedures, reliable cooperation by the client and early discussions as soon as deviations become apparent.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Contract claim. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/contract-claim/
Hain, D. (n.d.): Contract claim. PMDecoder. https://pmdecoder.com/en/glossary/contract-claim/ (retrieved 24 November 2026)
@misc{contractclaim,
author = {Hain, Dennis},
title = {Contract claim},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/contract-claim/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/contract-claim/"> <p>Demand by a contracting party for additional payment, more time or other entitlements arising from deviations from the contract</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/contract-claim/">Contract claim</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.