Last Planner System
Definition
The Last Planner System was developed for construction projects by Glenn Ballard and Greg Howell in the 1990s. The name refers to the last planning level before execution, such as the foremen and supervisors of the trades. Planning takes place in stages: a master schedule with milestones; phase schedules developed jointly from it, working backwards from the milestone; a look-ahead over several weeks in which constraints such as missing drawings, materials or permits are removed; and a weekly work plan in which only work that can actually be carried out is committed. The share of commitments kept is measured, and the reasons for deviations are analysed.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- Broader term
- Lean construction
- this term
- Last Planner System
Distinction
Traditional scheduling with the critical path method sets dates centrally and prescribes them. The Last Planner System relies on the commitments of those who do the work and above all steers the reliability of short-term plans. The two can be combined: the master schedule can come from network planning. Takt planning sets fixed time windows for areas; it is often combined with the Last Planner System.
In practice
During the construction of a school, the finishing trades fall behind because they keep encountering unfinished preceding work. Site management introduces a weekly meeting of all foremen. Each commits only to work for which drawings, materials and preceding work are ready and names constraints for the coming weeks. The share of commitments kept rises markedly within two months, and the finishing works recover some of the delay.
Frequently asked questions
Is the Last Planner System only suitable for construction?
It was developed for construction and is most widespread there. The idea of reliable commitments and removed constraints is, however, also used in plant engineering, maintenance and other projects.
Does the Last Planner System replace the schedule?
No. Master dates and milestones remain in place. The method adds joint short-term planning, which makes it more likely that these dates are met.
Source and context
Cite this entry
Last Planner System. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/last-planner-system/
Last Planner System (n.d.). PMDecoder. https://pmdecoder.com/en/glossary/last-planner-system/ (retrieved 24 November 2026)
@misc{lastplannersystem,
title = {Last Planner System},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/last-planner-system/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/last-planner-system/"> <p>Lean construction method in which the people carrying out the work plan it jointly in stages and make reliable commitments.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/last-planner-system/">Last Planner System</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.