Commitments

also: Committed costs, Open commitments

Definition

Commitments (German: Obligo) comprise all financial obligations arising from orders placed, purchase orders or contracts concluded for which no invoice has yet been received or booked. They show which part of the budget is already tied up. The budget that is actually still available is therefore the budget minus actual costs minus commitments.

Equivalents in other frameworks

No equivalents have been recorded for this term yet.

Classification

this term
Commitments

Distinction

Actual costs are booked costs; commitments are foreseeable costs from existing obligations. A forecast also estimates the costs of services not yet ordered. In German banking language, Obligo also denotes a liability, which shares only its origin with the controlling term.

In practice

A conversion project has a budget of two million euros, and 900,000 euros have been booked. The project manager believes 1.1 million euros are still available. Controlling points out that contracts worth 850,000 euros have been awarded but not yet invoiced. Only 250,000 euros are therefore actually free. The planned commissioning of new outdoor facilities for 300,000 euros is then postponed.

Frequently asked questions

Why are commitments so important for project control?

Because invoices often arrive weeks or months after the order has been placed. Without commitments, the budget appears larger than it is.

When are commitments reduced?

As soon as invoices are booked. The amount then moves from commitments to actual costs.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Commitments. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/commitments/

Short form

Hain, D. (n.d.): Commitments. PMDecoder. https://pmdecoder.com/en/glossary/commitments/ (retrieved 24 November 2026)

BibTeX
@misc{commitments,
  author  = {Hain, Dennis},
  title   = {Commitments},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/commitments/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/commitments/">
  <p>Amount for which a project has already entered into obligations, for example through purchase orders, that has not yet been booked as cost</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/commitments/">Commitments</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.