Commercial Management Approach
Definition
The commercial management approach describes how a PRINCE2 project shapes its business relationships with external suppliers. It records which services are bought in, how suppliers are selected, which types of contract are intended and how contracts are monitored and adjusted during the project. It also sets out how the obligations under the contracts fit with the project’s roles, plans and controls. The approach was added in PRINCE2 7 and reflects the fact that many projects obtain substantial parts of their outputs from third parties. It is created during initiation and becomes part of the project initiation documentation.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Distinction
General procurement covers the purchasing of services within an organization; the commercial management approach defines how this is done in a particular project. It does not replace the individual contract but places it in context. In the PMI world, a procurement management plan performs a comparable function.
In practice
A university is having its campus network renewed and awards design, hardware supply and installation to three firms. The commercial management approach specifies that installation is awarded at a fixed price, design is billed on a time basis and hardware is obtained under an existing framework agreement. It also determines that claims for extra work go through the project manager and must be approved by the project board above a set value.
Frequently asked questions
Does every project need a commercial management approach?
Only if services are obtained externally. If a project works exclusively with its own staff, the approach can be omitted or kept very brief.
How does it relate to the senior supplier?
The senior supplier represents the supplier side on the project board. If there are several external suppliers, the approach describes how their interests and obligations are integrated into project control.
Source and context
- Reference
- PRINCE2 7, Managementprodukte
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Commercial Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/commercial-management-approach/
Hain, D. (n.d.): Commercial Management Approach. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/commercial-management-approach/ (retrieved 24 November 2026)
@misc{commercialmanagementapproach,
author = {Hain, Dennis},
title = {Commercial Management Approach},
note = {PMDecoder, PRINCE2 7, Managementprodukte},
url = {https://pmdecoder.com/en/glossary/commercial-management-approach/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/commercial-management-approach/"> <p>PRINCE2 7 management product defining how procurement, contracts and working with suppliers are managed in the project.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/commercial-management-approach/">Commercial Management Approach</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer> </blockquote>
Found a mistake? Let us know, we check every report.