Project mandate or Project Mandate?
false friend · no overlap
Despite its name, the PRINCE2 Project Mandate is not the project mandate of ISO 21506. It is only the external trigger that starts project preparation.
| ISO 21506Project mandate | PRINCE2Project Mandate | |
|---|---|---|
| What it covers | Document that formally puts a project into effect and grants the project manager their authority. | In PRINCE2, the trigger from outside the project by which the commissioning body sets off the preparation of a project. |
| Equivalent in PMI / PMBOK Guide | Project charter equivalent | Project charter false friend |
| To the term page | Project mandate | Project Mandate |