Progress report or Project Progress Report?
closely related
Like the other reports, the Project Progress Report regularly states project status. In PM² the project manager sends it to the steering committee.
| ISO 21506Progress report | PM²Project Progress Report | |
|---|---|---|
| What it covers | Regular, brief report on the current state of a project covering progress, variances, risks and the decisions needed. | PM² report from the Project Manager to the Project Steering Committee on project status compared with the baselines and the Project Charter |
| Equivalent in PRINCE2 | Highlight Report closely related | Highlight Report closely related |
| To the term page | Progress report | Project Progress Report |