Return on investment
abbr. ROI
Definition
Return on investment indicates how much an investment yields in relation to its costs. In its simple form, the profit or net benefit is divided by the capital employed and expressed as a percentage. For projects, an ROI of fifty per cent means that the benefit exceeds the costs by half. It is easy to understand and is therefore widely used in business cases and decision papers.
Equivalents in other frameworks
No equivalents have been recorded for this term yet.
Classification
- this term
- Return on investment
- Topic area
- Cost and economic viability
Distinction
ROI does not take into account when costs and benefits arise; net present value, by contrast, discounts payments to a single point in time. The payback period indicates after what time the capital employed has been recovered. In corporate accounting, ROI also refers to the return on total capital, which relates to the company as a whole.
In practice
A logistics company is evaluating a project for automated route planning. Costs over three years: 400,000 euros for software, implementation and training. Expected savings on fuel and overtime over the same period: 620,000 euros. The net benefit of 220,000 euros results in an ROI of 55 per cent. Because most of the savings arise only in the third year, the controlling department also calculates the net present value.
Frequently asked questions
How do you calculate the ROI of a project?
As benefits minus costs, divided by costs, multiplied by one hundred. It is important to consider costs and benefits over the same period.
What are the limitations of ROI?
It ignores differences in timing and risks, and leaves out benefits that are difficult to quantify. For larger decisions it should be supplemented by other indicators.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Return on investment. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/return-on-investment/
Hain, D. (n.d.): Return on investment. PMDecoder. https://pmdecoder.com/en/glossary/return-on-investment/ (retrieved 24 November 2026)
@misc{returnoninvestment,
author = {Hain, Dennis},
title = {Return on investment},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/return-on-investment/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/return-on-investment/"> <p>Ratio that relates the profit or benefit of an investment to the capital employed</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/return-on-investment/">Return on investment</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.