Plans practice or Project planning?
closely related
In PRINCE2, the Plans practice covers making plans, as project planning does. It plans on several levels and starts from products, not activities.
| PRINCE2Plans practice | cross-frameworkProject planning | |
|---|---|---|
| What it covers | PRINCE2 7 practice describing how plans are prepared at several levels, starting from the products to be delivered. | Working out the path to the project result, covering scope, sequence, dates, resources, costs, risks and organization |
| To the term page | Plans practice | Project planning |