# Workaround

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Unplanned makeshift solution to an occurring problem](https://pmdecoder.com/en/concept/unplanned-makeshift-solution-to-an-occurring-problem/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/workaround/

## Definition

A workaround gets round a problem instead of fixing it at the root straight away. It arises under time pressure when something goes wrong that was not identified as a risk or not provided with a response. Workarounds keep a project going, but often at the expense of quality, cost or later effort. They should be documented and later replaced by a permanent solution.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Workaround](https://pmdecoder.com/en/glossary/workaround-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

A contingency plan is planned in advance; a workaround is improvised. In IT, the term also refers to the temporary circumvention of a known software defect until a fix is available. Frequent workarounds indicate that risk identification has gaps.

## In practice

Two days before a conference opens, the registration system fails, and the provider cannot help for a week. The team exports the latest participant data to a spreadsheet, prints name badges by mail merge and sets up a paper list at the entrance. The event goes ahead, but admission takes twice as long. In the debrief, a data export before every event is adopted as a standard precaution.

## Frequently asked questions

### Are workarounds bad?

Not in principle; they often save the day. They become a problem when they remain permanently and nobody fixes the actual cause.

### What should be done after a workaround?

Document the cause and the solution, plan a permanent fix and check whether similar risks are missing from the register.

## Related terms

- [Contingency plan](https://pmdecoder.com/en/glossary/contingency-plan/)
- [Issue](https://pmdecoder.com/en/glossary/issue/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.