# Workaround

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Unplanned makeshift solution to an occurring problem](https://pmdecoder.com/en/concept/unplanned-makeshift-solution-to-an-occurring-problem/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/workaround-pmi/

## Definition

In PMI terms, a workaround is a quick, temporary response to a problem that has already occurred. It is used when no response had been prepared for the event, for instance because the risk was not identified or was deliberately accepted passively, or when the planned response did not work. The workaround is meant to limit damage and keep work going but usually does not resolve the cause. It is therefore recorded, and a permanent solution follows, often through a corrective action or a change request.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Workaround](https://pmdecoder.com/en/glossary/workaround/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term corresponds to the cross-framework concept of a workaround. A contingency plan is prepared in advance and implemented on a defined trigger; a workaround is improvised. A corrective action brings performance permanently back into line with the plan, whereas a workaround merely bridges the gap. Frequent workarounds point to gaps in risk identification.

## In practice

The day before a series of training sessions, the learning platform fails, a risk that nobody had recorded. The project manager has the materials sent out as files and puts the exercises on a shared drive. The sessions go ahead. Afterwards the cause is investigated and the risk is added to the risk register.

## Frequently asked questions

### Is a workaround a sign of poor planning?

Not necessarily. Not every risk can be foreseen, and passively accepted risks lead to workarounds by design. Frequent workarounds, however, should prompt a review of risk work.

### What happens after a workaround?

It is documented, the cause is clarified and a permanent solution is agreed. The experience feeds into lessons learned.

## Related terms

- [Workaround](https://pmdecoder.com/en/glossary/workaround/)
- [Issue](https://pmdecoder.com/en/glossary/issue-pmi/)
- [Contingency plan](https://pmdecoder.com/en/glossary/contingency-plan-pmi/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action-pmi/)

---