# Work package

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.99 und 3.100
- Edition: ISO 21506:2024
- Concept: [Smallest planning unit of the project structure](https://pmdecoder.com/en/concept/smallest-planning-unit-of-the-project-structure/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/work-package/

## Definition

A work package is the unit in which work is planned, assigned and tracked. ISO 21506 describes it in two contexts. In project and programme management, it bundles related activities and forms part of a control account. For earned value management, every work package must be clearly delineated: what belongs to it, what comes out at the end, by when and at what cost? Only then can its progress be measured. In practice, it sits at the lowest level of the work breakdown structure and has a responsible person.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/) | equivalent | — |
| PRINCE2 | [Work Package](https://pmdecoder.com/en/glossary/work-package-prince2/) | closely related | In PRINCE2 above all an agreement between project manager and team manager on delivery, tolerances and reporting; can cover several products. |

## Distinction

An activity is a single task in the schedule, whereas a work package combines related activities into a unit with a result. A control account groups one or more work packages for reporting and control. The work package description records the details of a work package.

## In practice

In the construction of a new sports hall, the work package "Hall floor" comprises the activities check screed, lay substructure, install sports floor, apply court markings and acceptance. It has a budget of 180,000 euros, a timeframe of six weeks and, as its result, an accepted sports floor that meets the applicable standard. It belongs to the control account "Interior fit-out". Because content, result, timeframe and cost are defined, its progress can be assessed every month.

## Frequently asked questions

### How large should a work package be?

Large enough to deliver a meaningful, verifiable result and small enough to estimate effort, duration and cost reliably and to track progress. Common rules of thumb point to a few weeks of work, but none of them is binding.

### Who is responsible for a work package?

Each work package is assigned to a person or organizational unit that is accountable for its result. They plan the work within the package, report progress and flag deviations early.

### How does a work package differ from an activity?

The work package sits in the work breakdown structure and describes which result is to be produced. Activities sit in the schedule and describe tasks with durations and dependencies. One work package can comprise several activities.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)
- [Activity](https://pmdecoder.com/en/glossary/activity/)
- [Work package description](https://pmdecoder.com/en/glossary/work-package-description/)
- [Work breakdown structure element](https://pmdecoder.com/en/glossary/work-breakdown-structure-element/)

---