# Work package

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Smallest planning unit of the project structure](https://pmdecoder.com/en/concept/smallest-planning-unit-of-the-project-structure/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Canonical version: https://pmdecoder.com/en/glossary/work-package-pmi/

## Definition

In PMI usage, a work package is the work that forms the bottom tier of the work breakdown structure; cost and duration are estimated and managed for it. It describes a clearly delimited partial result with clear responsibility and is explained in more detail in the WBS dictionary. For scheduling, it is broken down into individual activities. In earned value management, work packages are assigned to a control account, where scope, budget and schedule are brought together and compared with actual performance.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Work package](https://pmdecoder.com/en/glossary/work-package/) | equivalent | — |
| PRINCE2 | [Work Package](https://pmdecoder.com/en/glossary/work-package-prince2/) | closely related | In PRINCE2 above all an agreement between project manager and team manager on delivery, tolerances and reporting; can cover several products. |

## Distinction

The work package as defined in ISO 21506 denotes the same thing; this entry gives the PMI view. A planning package is a placeholder for later work that has not yet been elaborated into work packages. An activity is a task in the schedule, a work package a part of the scope; one work package usually contains several activities.

## In practice

In the project to introduce a customer portal, one work package is called “Interface to billing system”. A development team is responsible for it, and the estimate is 40 person-days and six weeks. The package is complete when the interface has been tested with real invoice data and accepted by the billing department. In the schedule it is broken down into specification, implementation, testing and acceptance.

## Frequently asked questions

### How large should a work package be?

Large enough to be estimated reliably, handed to a responsible owner and tracked within the reporting cycle. A common rule of thumb is a few days to a few weeks of work; PMI does not set a fixed size.

### Can a work package have several owners?

Several people can work on it, but one party should be accountable. Otherwise it is unclear who has to act in the event of delays or defects.

## Related terms

- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Control account](https://pmdecoder.com/en/glossary/control-account-pmi/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [WBS dictionary](https://pmdecoder.com/en/glossary/wbs-dictionary/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
