# Work package description

also: Work package specification

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Description of work breakdown structure elements](https://pmdecoder.com/en/concept/description-of-work-breakdown-structure-elements/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/work-package-description/

## Definition

The work package description adds to the work breakdown structure the details needed to plan, assign and control a work package. Typical information includes the WBS code and name, objective and content, the results to be produced, the boundary with neighbouring packages, prerequisites, the responsible person, planned effort, costs, dates and acceptance criteria. The full set of descriptions is also referred to as the work breakdown structure dictionary.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Work breakdown structure dictionary](https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/) | partially overlapping | describes a single work package, not all elements of the work breakdown structure |
| PMI / PMBOK Guide | [WBS dictionary](https://pmdecoder.com/en/glossary/wbs-dictionary/) | partially overlapping | describes a single work package, not all elements of the work breakdown structure |
| PRINCE2 | [Product Description](https://pmdecoder.com/en/glossary/product-description/) | partially overlapping | Describes products rather than work and defines quality criteria, checking methods and responsibilities. |

## Distinction

The work breakdown structure shows the breakdown, the work package description the content of a single element. A statement of work is addressed to an external contractor and forms part of the contract; the work package description serves internal control, but can be used as a basis for a statement of work. An activity list contains activities with durations, while the work package description also covers results and responsibility.

## In practice

In a project to introduce a document management system, the finance department is given the work package "Define filing structure for accounting". The one-page description specifies as its result an approved folder structure with retention periods, together with the responsible team leader, five person-days of effort, the deadline and the dependency on the requirements of internal audit. When internal audit later raises further requirements, the change can be clearly distinguished from the original assignment.

## Frequently asked questions

### How detailed should a work package description be?

One page is usually enough. What matters is that the result, responsibility, effort and boundaries are unambiguous.

### Who prepares the description?

The person responsible for the work package together with the project manager, so that both sides stand behind the scope and effort.

## Related terms

- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [WBS code](https://pmdecoder.com/en/glossary/wbs-code/)
- [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria/)

---