# Work item

- Framework: [Kanban](https://pmdecoder.com/en/framework/kanban/)
- Reference: Kanban Guide 2025.5, Abschnitt Defining and Visualizing the Workflow
- Edition: The Kanban Guide, May 2025
- Concept: [Item in an ordered work list](https://pmdecoder.com/en/concept/item-in-an-ordered-work-list/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/work-item/

## Definition

According to the Kanban Guide, work items are the single units of value moving through a workflow, also called items for short. What a work item is, the members specify in the Definition of Workflow: a customer order, a support request, an article, a software feature or an application. For each work item it must be clear when it counts as started and when as finished; depending on its type, there may be several start or end points. Between start and finish it passes through the defined states and counts as work in progress for that period. All four flow metrics relate to work items, which is why how they are defined determines how meaningful the data is.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| Scrum | [Product Backlog item](https://pmdecoder.com/en/glossary/product-backlog-item/) | closely related | need not come from a backlog; the focus is on its flow through the Kanban system |

## Classification

- Broader term: [Definition of Workflow](https://pmdecoder.com/en/glossary/definition-of-workflow/)

## Distinction

A Product Backlog item in Scrum and a work item in Kanban can describe the same thing; the Kanban Guide, however, regards it primarily as a unit that is counted and whose passage is measured. A work package in traditional planning is a unit of breakdown, not something whose flow is managed. The card on the Kanban board is merely the representation of a work item.

## In practice

An HR department specifies that a work item is a vacancy to be filled, not an individual application. It starts with the approval of the job advertisement and ends with the signed acceptance. Initially, the team had tracked each application as a separate item; the throughput figures then said nothing about how quickly positions were actually filled.

## Frequently asked questions

### Do all work items have to be the same size?

No. The Kanban Guide does not require work items to be estimated or made equal in size. Throughput counts the exact number of items, regardless of their size.

### Can a Kanban system have different types of work items?

Yes. The Definition of Workflow can describe several types, such as bug fixes and new features, each with its own start and end points.

## Related terms

- [Product Backlog item](https://pmdecoder.com/en/glossary/product-backlog-item/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Throughput](https://pmdecoder.com/en/glossary/throughput/)

---