# Work Item Age

also: Item age

- Framework: [Kanban](https://pmdecoder.com/en/framework/kanban/)
- Reference: Kanban Guide 2025.5, Abschnitt Flow Metrics
- Edition: The Kanban Guide, May 2025
- Canonical version: https://pmdecoder.com/en/glossary/work-item-age/

## Definition

Work Item Age measures how much time has passed from the start of a work item up to now. It applies only to items that are not yet finished and grows with every day an item remains in the workflow. Of the four flow metrics, it is the only one that relates to individual items in progress, whereas throughput and cycle time only arise after completion. This makes it an early warning signal: comparing the age of items in progress with the Service Level Expectation reveals items that are taking too long before they miss the forecast. The Kanban Guide names not letting items age unnecessarily as part of active management.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Flow metrics](https://pmdecoder.com/en/glossary/flow-metrics/)

## Distinction

Cycle time measures the total duration of a completed item, Work Item Age the current status of an item in progress. It shares with schedule slippage in traditional planning the fact that it points to delays, but it does not relate to a planned date; it relates to the system's past experience.

## In practice

The IT department of a hospital shows on its board, next to each card, how many days a job has been running. Its Service Level Expectation is: 80 percent of jobs within ten days. On Tuesday, two jobs are at eight days. Instead of starting new jobs, the team supports the colleague responsible, and both jobs are done by Thursday.

## Frequently asked questions

### Why is Work Item Age so important?

Because it provides information while the work is still under way. This makes it possible to intervene before an item exceeds its expected duration.

### How is age displayed?

Often as a number or dots on the card, or in a chart that shows each item in progress by state and age, frequently together with the Service Level Expectation.

## Related terms

- [Service Level Expectation](https://pmdecoder.com/en/glossary/service-level-expectation/)
- [Cycle Time](https://pmdecoder.com/en/glossary/cycle-time/)
- [Blocked work](https://pmdecoder.com/en/glossary/blocked-work/)

---