# Work breakdown structure

abbr. WBS

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.96
- Edition: ISO 21506:2024
- Concept: [Hierarchical decomposition of project scope](https://pmdecoder.com/en/concept/decomposing-project-scope/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/work-breakdown-structure/

## Definition

Hierarchical breakdown of everything a project or programme has to accomplish into ever smaller components until, at the lowest level, work packages emerge that can be planned, estimated and assigned. The work breakdown structure shows **what** needs to be done, not when and not by whom.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/) | equivalent | identical understanding, more detailed rules on decomposition depth |
| PRINCE2 | [Product Breakdown Structure](https://pmdecoder.com/en/glossary/product-breakdown-structure-prince2/) | partially overlapping | Breakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506. |
| Scrum | [Product Backlog](https://pmdecoder.com/en/glossary/product-backlog/) | partially overlapping | also decomposes the scope, but ordered by value rather than hierarchically |

## Distinction

The work breakdown structure shows what needs to be done, the schedule when it happens and the responsibility assignment matrix who is involved. The product breakdown structure breaks down the result, the work breakdown structure the work needed to produce it. The work breakdown structure dictionary describes its individual elements.

## In practice

A municipal utility plans to replace 40 kilometres of water mains. At the first level, the work breakdown structure is divided into design, permits, civil works, pipe laying, house connections, traffic management and project management. When it is checked against the 100 % rule, it turns out that informing local residents is not contained in any element. This is added as a separate work package under traffic management. Each of the 46 work packages is then given a responsible person and a budget.

## Frequently asked questions

### How does the work breakdown structure differ from the schedule?

The work breakdown structure shows all the work that has to be done and divides it into components. When and in which order the work happens is only set out in the schedule, which builds on the work packages.

### How far is a work breakdown structure decomposed?

Far enough that the lowest level consists of work packages that can be reliably estimated, assigned to a responsible party and tracked for progress. There is no fixed number of levels. Too much detail creates administrative effort, too little prevents effective control.

### How can a work breakdown structure be organized?

Common options are to organize it by the components of the result, by activities or by phases, often in combination. What matters is that the entire project scope is covered completely and that the elements do not overlap.

## Related terms

- [Hierarchical decomposition](https://pmdecoder.com/en/glossary/hierarchical-decomposition/)
- [100 % rule](https://pmdecoder.com/en/glossary/100-percent-rule/)
- [Work breakdown structure element](https://pmdecoder.com/en/glossary/work-breakdown-structure-element/)
- [Work breakdown structure dictionary](https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Product breakdown structure](https://pmdecoder.com/en/glossary/product-breakdown-structure/)

---