# Work breakdown structure element

also: WBS element

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.98
- Edition: ISO 21506:2024
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/work-breakdown-structure-element/

## Definition

A work breakdown structure element represents a defined part of the work at a fixed position in the work breakdown structure. It has a unique identifier, usually a code such as 2.3.1 that shows its level and position, and a name. Every element is a parent, because it has been broken down further, or sits below another element as its child; most elements are both at once. The elements at the lowest level are usually work packages.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A work package is an element at the lowest level, but not every element is a work package. An activity belongs to the schedule, not to the work breakdown structure. A control account can correspond to an element but is also defined by its assignment to an organizational unit.

## In practice

A construction project uses a four-level code. Element 2.4 stands for building services, 2.4.3 for ventilation and 2.4.3.2 for installing the ventilation system in the second construction phase. Because accounting and scheduling use the same code, the costs and dates of each element can be combined directly. When a further construction phase is added, it receives the free number 2.4.3.3 without any existing codes having to change.

## Frequently asked questions

### How are work breakdown structure elements numbered?

Usually with a hierarchical code in which each level adds a digit, such as 1, 1.2, 1.2.3. It is important that codes remain stable after approval, because costs and reports depend on them.

### What information belongs to an element?

At least an identifier and a name. More detailed information such as content, responsibility and results is kept in the work breakdown structure dictionary.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Parent element](https://pmdecoder.com/en/glossary/parent-element/)
- [Work breakdown structure dictionary](https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Control account](https://pmdecoder.com/en/glossary/control-account/)

---