# WBS dictionary

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Description of work breakdown structure elements](https://pmdecoder.com/en/concept/description-of-work-breakdown-structure-elements/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Canonical version: https://pmdecoder.com/en/glossary/wbs-dictionary/

## Definition

In PMI usage, the WBS dictionary is a document that gives detailed information on deliverables, activities and scheduling for every element of the work breakdown structure. Typical entries are the identifier from the code of accounts, a description of the work, the responsible organization, assumptions and constraints, milestones, associated activities, required resources, cost estimates, quality requirements and acceptance criteria. Together with the scope statement and the work breakdown structure, it forms the approved scope baseline in predictive approaches.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Work breakdown structure dictionary](https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/) | equivalent | — |
| PRINCE2 | [Product Description](https://pmdecoder.com/en/glossary/product-description/) | partially overlapping | Describes products rather than work and defines quality criteria, checking methods and responsibilities. |
| cross-framework | [Work package description](https://pmdecoder.com/en/glossary/work-package-description/) | partially overlapping | describes a single work package, not all elements of the work breakdown structure |

## Distinction

The WBS dictionary as defined in ISO 21506 denotes the same thing; this entry gives the PMI view. A work package description is limited to the lowest level, whereas the WBS dictionary can describe every component of the structure. The work breakdown structure shows the breakdown, the WBS dictionary explains what lies behind each component.

## In practice

In a project to modernize a tram line, the WBS dictionary entry for 3.4 “Make stops step-free” reads: eight stops, platform height as specified by the transport operator, responsibility with the civil engineering department, work only during night-time closures, acceptance by the supervisory authority. When a construction firm asks how many tactile guidance strips are needed, site management finds the answer there instead of piecing it together from several documents.

## Frequently asked questions

### Does the WBS dictionary have to be completed in full for every component?

No. Which details are needed depends on the size and risk of the project. A full description is worthwhile for work packages, while purpose and responsibility are often enough for higher-level components.

### Who maintains the WBS dictionary?

Usually the project manager or project office together with the work package owners. Changes to the approved version go through the change procedure.

## Related terms

- [Work breakdown structure dictionary](https://pmdecoder.com/en/glossary/work-breakdown-structure-dictionary/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Code of accounts](https://pmdecoder.com/en/glossary/code-of-accounts/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Work package description](https://pmdecoder.com/en/glossary/work-package-description/)

---