# WBS code

also: WBS number, WBS identifier

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Identifier of work breakdown structure elements](https://pmdecoder.com/en/concept/identifier-of-work-breakdown-structure-elements/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/wbs-code/

## Definition

The WBS code uniquely identifies every subproject, sub-task and work package in the work breakdown structure. A structure that reflects the hierarchy is common, for example 2.3.1 for the first work package of the third sub-task in the second subproject. The code is used to assign effort, costs, dates, responsibilities and documents to the elements, so that analyses are possible at every level.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Code of accounts](https://pmdecoder.com/en/glossary/code-of-accounts/) | closely related | denotes the entire numbering system, the WBS code the individual identifier |

## Distinction

The WBS code identifies an element of the work breakdown structure, whereas an activity number identifies an activity in the schedule; a work package can comprise several activities. Cost centres and cost units in accounting are separate classification systems that are often linked via the WBS code. A distinction is made between classifying codes, which express characteristics of content, and identifying codes, which merely number the elements uniquely.

## In practice

A plant manufacturer uses a uniform WBS code for all its projects: the first digit stands for the phase, the second for the trade and the third for the work package. Fitters book their hours to these codes, and supplier invoices are assigned to them. This allows the project manager to see at any time what, for example, the electrical engineering has cost in the installation phase, and to compare the figures with other projects later.

## Frequently asked questions

### Should a WBS code be changed afterwards?

Preferably not, because bookings, documents and analyses depend on it. New elements are given new codes, and codes of elements that have been dropped are blocked rather than reassigned.

### Does every project need a WBS code?

Yes, as soon as costs or hours are booked to work packages. For small projects, simple numbering is sufficient.

## Related terms

- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)
- [Work package description](https://pmdecoder.com/en/glossary/work-package-description/)
- [Decomposition](https://pmdecoder.com/en/glossary/decomposition/)

---