# Verification

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Evidence that requirements are met](https://pmdecoder.com/en/concept/evidence-that-requirements-are-met/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Canonical version: https://pmdecoder.com/en/glossary/verification-pmi/

## Definition

For PMI, verification is the evaluation of whether a result conforms to what was specified for it: a requirement, a technical specification, a regulation or a contractual condition. It is usually performed within the project, for instance by checks, measurements, tests, inspections or reviews. Its outcome is verified deliverables that can then be presented to the customer for acceptance. Verification presupposes that requirements are stated clearly and testably; vague requirements cannot be verified.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Verification](https://pmdecoder.com/en/glossary/verification/) | equivalent | — |

## Distinction

The PMI term corresponds to the concept described in the glossary under the cross-framework term “Verifizierung” (verification). Verification asks whether the thing was built right, validation whether the right thing was built. In the process-based editions of the PMBOK Guide, verification sat with quality control and validation with the customer’s confirmation of scope. A quality audit, by contrast, examines processes rather than individual results.

## In practice

For a bridge railing, the specification prescribes a certain height and a minimum load. The site management has the height measured at twenty points and load tests carried out on three segments. All values are within the permitted range, and the report is attached to the deliverable. Only then is the handover to the client prepared.

## Frequently asked questions

### How are verification and validation related?

Verification comes first and ensures that the result matches what was specified. Validation builds on it and clarifies with the customer whether the result is fit for purpose. Both are needed; neither replaces the other.

### What does good verification require?

Testable requirements with measurable criteria, suitable test methods and traceable documentation of the results. A mapping of which test covers which requirement is helpful.

## Related terms

- [Verification](https://pmdecoder.com/en/glossary/verification/)
- [Validation](https://pmdecoder.com/en/glossary/validation-pmi/)
- [Requirement](https://pmdecoder.com/en/glossary/requirement-pmi/)
- [Quality audit](https://pmdecoder.com/en/glossary/quality-audit/)
- [Quality control](https://pmdecoder.com/en/glossary/quality-control/)

---