# Variance

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.93
- Edition: ISO 21506:2024
- Concept: [Difference between plan and actual](https://pmdecoder.com/en/concept/difference-between-plan-and-actual/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/variance/

## Definition

A variance arises when actual results do not match the plan. The yardstick is not the current planning status at any given time but the approved baseline. Variances can concern schedule, cost, scope or quality and can be favourable or unfavourable. They are expressed in units such as days or euros, or as a percentage, and compared with variance thresholds to decide whether action is needed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Variance](https://pmdecoder.com/en/glossary/variance-pmi/) | equivalent | — |

## Distinction

Variance analysis is the procedure for determining variances and investigating their causes. Cost variance and schedule variance are particular variances calculated with the earned value method. An issue is a problem that has occurred and may, but need not, cause a variance.

## In practice

In the monthly report of a building project, the structural work shows a schedule variance of twelve working days and a cost variance of plus 40,000 euros. Site management attributes the delay to frost, which halted the concrete work; the work already performed, by contrast, cost somewhat less than budgeted. Because the schedule variance exceeds the agreed threshold of ten days, site management presents a plan for catching up; the cost variance requires no action.

## Frequently asked questions

### Is every variance a problem?

No. Small variances are normal, because no plan predicts reality exactly. What matters is whether they exceed agreed thresholds or show a trend.

### Why measure against the baseline and not the current plan?

Because the current plan is adjusted continuously. If it were used as the yardstick, variances would vanish as soon as the plan had been updated, and the project's development could no longer be traced.

## Related terms

- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Variance threshold](https://pmdecoder.com/en/glossary/variance-threshold/)
- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)
- [Cost variance](https://pmdecoder.com/en/glossary/cost-variance/)
- [Schedule variance](https://pmdecoder.com/en/glossary/schedule-variance/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion/)

---