# Variance threshold

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.95
- Edition: ISO 21506:2024
- Concept: [Permitted margin for deviations](https://pmdecoder.com/en/concept/permitted-margin-for-deviations/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/variance-threshold/

## Definition

Variance thresholds sort out which variances the project absorbs itself and which call for a response. They are set before work starts, usually separately for schedule, cost and scope, and stated as absolute values or percentages, such as ten working days or five per cent of the budget. As long as a variance stays below the threshold, monitoring is enough. Once it is reached, it must be examined whether corrective action, a change to the plan or escalation to the next level up is required.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Tolerance (PRINCE2)](https://pmdecoder.com/en/glossary/tolerance-prince2/) | equivalent | — |

## Distinction

Risk tolerance relates to possible future events, the variance threshold to differences from the baseline that have already occurred. In PRINCE2, comparable limits are called tolerances and are firmly tied to escalation between management levels. A specification limit in quality control, by contrast, concerns characteristics of a product, not the course of the project.

## In practice

A district council is having twelve schools refurbished as a programme. The rule for each project is: variances of up to five per cent of cost or two weeks of delay are handled by the project manager, up to ten per cent or four weeks by the programme manager, and anything beyond that by the district committee. When hazardous substances found at one school raise costs by eight per cent, the project manager presents two options to the programme manager; the committee does not need to be involved.

## Frequently asked questions

### How are sensible variance thresholds set?

According to the importance of the characteristic and the uncertainty of the planning. Tight thresholds suit undertakings that can be planned well, wider ones suit novel undertakings. Thresholds that are too tight lead to constant escalation, and thresholds that are too wide mean problems are noticed late.

### Do thresholds only apply to individual values?

Not only. Many organizations also set trend thresholds, for example when a performance index deteriorates for three reporting periods in a row, even if the value itself is still within limits.

## Related terms

- [Variance](https://pmdecoder.com/en/glossary/variance/)
- [Risk tolerance](https://pmdecoder.com/en/glossary/risk-tolerance/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Variance at completion](https://pmdecoder.com/en/glossary/variance-at-completion/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.