# Variance analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Examining plan-versus-actual differences](https://pmdecoder.com/en/concept/examining-plan-versus-actual-differences/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/variance-analysis-pmi/

## Definition

In PMI usage, variance analysis is a technique for establishing why and by how much actual performance differs from the baseline. It answers three questions: how large is the variance, where does it come from, and what does it mean for the rest of the project? It draws on performance measurement indicators such as schedule variance and cost variance, but also on variances in scope, quality or resources. The result is an explanation of the variance and a recommendation on whether and how to respond.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/) | equivalent | — |

## Distinction

The term corresponds to the cross-framework term variance analysis. The variance is the measurement result, variance analysis its investigation. Root cause analysis goes deeper and looks for the underlying cause of a problem; it can be part of a variance analysis. Trend analysis looks at development across several status dates instead of the variance at one point in time.

## In practice

In the monthly report of an infrastructure project, the cost variance is minus 6 percent and therefore above the 5 percent threshold. Variance analysis breaks the variance down by control account: two thirds come from higher steel prices, one third from rework on a bridge bearing. A change request is raised for the price increase, and a corrective action in quality assurance is agreed for the rework.

## Frequently asked questions

### Does every variance have to be analysed?

Usually only variances that exceed defined thresholds. This focuses effort on what matters. Thresholds are set during planning, often graded by level.

### What belongs in the result of a variance analysis?

The size of the variance, its causes, the likely consequences for schedule and cost, and a recommendation for action or the reasons why none is needed.

## Related terms

- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)
- [Variance](https://pmdecoder.com/en/glossary/variance-pmi/)
- [Root cause analysis](https://pmdecoder.com/en/glossary/root-cause-analysis-pmi/)
- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis-pmi/)
- [Corrective action](https://pmdecoder.com/en/glossary/corrective-action-pmi/)

---