# Validation

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Evidence of fitness for purpose](https://pmdecoder.com/en/concept/evidence-of-fitness-for-purpose/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Canonical version: https://pmdecoder.com/en/glossary/validation-pmi/

## Definition

For PMI, validation is the assurance that a result is fit for its intended purpose. The question is not whether something was built to specification but whether it satisfies the customer and other relevant stakeholders in actual use. In PMI’s understanding, validation usually ends with the formal acceptance of a deliverable by the customer or sponsor. The yardsticks are requirements, acceptance criteria and the expectations behind them. In adaptive approaches validation happens continuously, for example when an increment is demonstrated; in predictive approaches it tends to be bundled at the end of phases.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Validation](https://pmdecoder.com/en/glossary/validation/) | equivalent | — |

## Distinction

Validation belongs to the concept described in the glossary under the cross-framework term “Validierung” (validation); the PMI term is equivalent. Its counterpart is verification, which checks conformance with a requirement, specification or regulation. In the process-based editions of the PMBOK Guide, validation followed quality control: deliverables were first checked and then accepted by the customer. Acceptance in the contractual sense is the legal consequence, not the technical evaluation itself.

## In practice

A team develops a warehouse scanner app for a logistics company. All tests against the specification have been passed. During validation, two shift supervisors work with the app for a week and find that it can hardly be operated while wearing work gloves. The team enlarges the buttons, and the sponsor then formally accepts the app.

## Frequently asked questions

### Who carries out validation?

It is carried out by the customer, sponsor or future users, because only they can judge whether the purpose has been met. The project team prepares it, provides the results and documents the decision.

### Can a verified result fail validation?

Yes. If the requirements did not capture the real need correctly, the result meets the specification and is still not usable. Validation is meant to reveal exactly this gap.

## Related terms

- [Validation](https://pmdecoder.com/en/glossary/validation/)
- [Verification](https://pmdecoder.com/en/glossary/verification-pmi/)
- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)
- [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria-pmi/)
- [Requirement](https://pmdecoder.com/en/glossary/requirement-pmi/)
- [Sprint Review](https://pmdecoder.com/en/glossary/sprint-review/)

---