# Trend analysis

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Evaluating development across several data dates](https://pmdecoder.com/en/concept/evaluating-development-across-several-data-dates/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/trend-analysis/

## Definition

In trend analysis, values such as dates, costs, percent complete or defect counts are examined across several points in time. The course of the values shows whether a quantity remains stable, improves or deteriorates, and where it is heading if the development continues unchanged. This makes problems visible before they show up in a single plan-versus-actual comparison.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis-pmi/) | equivalent | — |

## Other terms

- Milestone trend analysis (related, not equivalent)
- MTA (related, not equivalent)

## Distinction

Variance analysis looks at one point in time, trend analysis at a series. Milestone trend analysis is a common special form in which the currently expected dates of milestones are plotted in a chart across the reporting dates. A forecast can be based on a trend analysis but often uses further information.

## In practice

In a construction project, the project manager estimates each month the expected completion date for the structural shell. In the milestone trend analysis chart, the line rises slightly three months in a row, although each individual slip amounts to only a few days. The project manager treats this as a warning sign and clarifies the staffing situation with the shell construction contractor. The cause is a shortage of formwork carpenters, which is remedied with a subcontractor.

## Frequently asked questions

### How do you read a milestone trend analysis?

Horizontal lines mean stable dates, rising lines slips to later dates, falling lines improvements. If many lines rise at the same time, this points to a fundamental planning problem.

### How many data points does a trend analysis need?

It becomes meaningful from about three to four measurements. It is important that the values are always collected in the same way.

## Related terms

- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis/)
- [Project forecast](https://pmdecoder.com/en/glossary/project-forecast/)
- [Milestone](https://pmdecoder.com/en/glossary/milestone/)
- [Historical data](https://pmdecoder.com/en/glossary/historical-data/)

---