# Trend analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Evaluating development across several data dates](https://pmdecoder.com/en/concept/evaluating-development-across-several-data-dates/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/trend-analysis-pmi/

## Definition

In PMI usage, trend analysis is an analytical technique that uses mathematical or statistical models to forecast future developments on the basis of past results. In a project, performance data are examined over several reporting periods, for example earned value indicators, defect counts, throughput or resource consumption. What matters is not the individual value but the direction and speed of change. This shows whether a situation is improving or deteriorating long before an objective is missed. The results feed into forecasts and into decisions on corrective or preventive actions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis/) | equivalent | — |

## Distinction

The term corresponds to the cross-framework term trend analysis; milestone and cost trend analysis are specific forms of it. Variance analysis looks at the variance at a status date and asks about causes, whereas trend analysis looks at development over time. A forecast is the result to which trend analysis can contribute.

## In practice

In a software project, the cost performance index falls from 1.02 to 0.91 over four months. Each individual value is still within the agreed tolerance, but trend analysis shows a steady decline. If it continues, the tolerance will be exceeded in two months. The project manager investigates the cause, finds increasing effort for unplanned interfaces and raises a preventive action.

## Frequently asked questions

### How many data points does trend analysis need?

At least three, preferably more, so that a direction can be distinguished from random fluctuation. The data points should be determined using the same method; otherwise spurious trends arise.

### Can a trend simply be extrapolated linearly?

For short periods this is often sufficient. Over longer periods, however, conditions change, for example through learning curves or new project phases, and a reasoned judgement is needed.

## Related terms

- [Trend analysis](https://pmdecoder.com/en/glossary/trend-analysis/)
- [Cost trend analysis](https://pmdecoder.com/en/glossary/cost-trend-analysis/)
- [Forecast](https://pmdecoder.com/en/glossary/forecast/)
- [Variance analysis](https://pmdecoder.com/en/glossary/variance-analysis-pmi/)
- [S-curve analysis](https://pmdecoder.com/en/glossary/s-curve-analysis/)
- [Preventive action](https://pmdecoder.com/en/glossary/preventive-action-pmi/)

---