# Total float

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Scheduling flexibility relative to project completion](https://pmdecoder.com/en/concept/scheduling-flexibility-relative-to-project-completion/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/total-float-pmi/

## Definition

In PMI’s understanding, total float states how far an activity can be shifted from its early start date before the project finish date moves or a defined schedule constraint is breached. The critical path method calculates it as the difference between the late and early start, or between the late and early finish, of an activity. Activities on the critical path usually have zero total float. A negative value shows that the schedule cannot meet a constraint, such as a contractually agreed finish date. Total float does not belong to a single activity alone but to the whole path: if one activity uses up the margin, it is no longer available to its successors on the same path.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Total float](https://pmdecoder.com/en/glossary/total-float/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Total float corresponds to the German term Gesamtpuffer. It differs from free float in its reference point: free float measures only the margin up to the early start of the immediate successor, total float the margin up to the project finish. An explicitly planned time reserve, such as a project buffer in the critical chain method, is not float but a separate element of the plan.

## In practice

When planning a trade fair appearance, the schedule calculation shows total float of twelve working days for the activity “Print promotional materials”. The graphics department wants to postpone print approval by a week. The project manager agrees but points out that only seven days of margin will then remain for the entire path up to shipping. He records the consumed float in the status report so that later delays on this path are noticed early.

## Frequently asked questions

### What does negative total float mean?

The schedule cannot meet a defined constraint, usually an imposed finish date. The number shows by how many time units the path is too long. Remedies include fast tracking, crashing, a change in scope or a renegotiated constraint.

### May the team use total float freely?

Technically yes, but the margin is shared by all activities on a path. Many organizations therefore define who decides on its use, and some contracts specify who owns the float.

## Related terms

- [Total float](https://pmdecoder.com/en/glossary/total-float/)
- [Free float](https://pmdecoder.com/en/glossary/free-float-pmi/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)
- [Critical path method](https://pmdecoder.com/en/glossary/critical-path-method-pmi/)
- [Late start date](https://pmdecoder.com/en/glossary/late-start-date-pmi/)