# Total cost of ownership

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Total costs over the service life](https://pmdecoder.com/en/concept/total-costs-over-the-service-life/)
- Topic area: [Cost and economic viability](https://pmdecoder.com/en/area/cost-and-economic-viability/)
- Canonical version: https://pmdecoder.com/en/glossary/total-cost-of-ownership-pmi/

## Definition

PMI uses total cost of ownership to denote the entire cost that a project result causes over its whole life cycle. Besides the costs of development or procurement, this includes implementation, training, operation, maintenance, further development and finally decommissioning and disposal. In this way, PMI directs attention beyond the end of the project: a project is meant to create value, and this value can only be judged if the follow-on costs of the result are known. Decisions within the project, for example between a low-cost and a low-maintenance solution, should therefore not be made on project costs alone. The analysis feeds into the business case and benefits planning.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Total cost of ownership](https://pmdecoder.com/en/glossary/total-cost-of-ownership/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

PMI uses the term with the same meaning as the cross-framework term of the same name; its particular feature lies in the link to the value the project is meant to create. It differs from the project budget in its time frame: the budget covers only the project duration, total cost of ownership the whole period of use of the result.

## In practice

A hospital compares two systems for electronic patient records. System A costs 400,000 euros to implement, system B 550,000 euros. Calculated over ten years, however, A causes around 1.9 million euros because of annual licence and customization costs, and B only 1.5 million euros. The business case is based on this overall view, and the project recommends system B despite its higher initial cost.

## Frequently asked questions

### Why does total cost of ownership matter to a project that ends at handover?

Because decisions made in the project determine the follow-on costs, for example on technology, quality or maintainability. Minimizing only the project costs can cause higher overall costs for the organization.

### Which costs are easily forgotten in total cost of ownership?

Often overlooked are internal staff costs for operation and support, training when staff change, costs of adapting to new regulations, and the effort for data migration and decommissioning at the end.

## Related terms

- [Total cost of ownership](https://pmdecoder.com/en/glossary/total-cost-of-ownership/)
- [Product life cycle](https://pmdecoder.com/en/glossary/product-life-cycle-pmi/)
- [Business case](https://pmdecoder.com/en/glossary/business-case-pmi/)
- [Benefits](https://pmdecoder.com/en/glossary/benefits/)
- [Net present value](https://pmdecoder.com/en/glossary/net-present-value/)

---