# Tollgate

- Framework: [Six Sigma](https://pmdecoder.com/en/framework/six-sigma/)
- Concept: [Decision point between project phases](https://pmdecoder.com/en/concept/decision-point-between-project-phases/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Canonical version: https://pmdecoder.com/en/glossary/tollgate/

## Definition

A tollgate is a review at the transition between two phases of a Six Sigma project. The team presents what it has achieved in the completed phase and shows that the expected results are in place, such as an agreed project charter after Define or confirmed causes after Analyze. The champion, often together with the process owner and a Master Black Belt, reviews these results and decides whether the project moves into the next phase, is reworked, redirected or ended. Tollgates thus create fixed opportunities to review resources and priorities and prevent a project from continuing without a sound basis.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Gate](https://pmdecoder.com/en/glossary/gate/) | closely related | between the phases of the DMAIC cycle |
| PMI / PMBOK Guide | [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/) | closely related | between the phases of the DMAIC cycle |
| PM² | [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/) | closely related | between the phases of the DMAIC cycle |
| PRINCE2 | [Managing a stage boundary](https://pmdecoder.com/en/glossary/managing-a-stage-boundary/) | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |

## Distinction

In essence the tollgate corresponds to the gate in ISO 21506 and the PMI phase gate. It is, however, tied to the five DMAIC phases, and its review questions concern the data and evidence of the improvement project rather than budget and schedule. A regular status meeting does not replace it, because no approval of the next phase takes place there.

## In practice

After the Measure phase a Green Belt presents the error rate in order entry to the champion. The Master Black Belt notices that two sites count errors differently. The champion does not yet release the Analyze phase and allows two weeks to align the definition and collect the data again.

## Frequently asked questions

### Can a project be ended at a tollgate?

Yes. If it turns out, for example, that the problem is smaller than assumed or a simple solution is already enough, stopping is a sensible decision and not a failure.

### Who prepares a tollgate?

The project lead, usually a Black Belt or Green Belt. They compile the results of the phase and name open issues and risks for the next phase.

## Related terms

- [Gate](https://pmdecoder.com/en/glossary/gate/)
- [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/)
- [DMAIC](https://pmdecoder.com/en/glossary/dmaic/)
- [Champion](https://pmdecoder.com/en/glossary/champion/)
- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)

---