# Tolerance (PRINCE2)

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Fortschritt
- Edition: PRINCE2 7
- Concept: [Permitted margin for deviations](https://pmdecoder.com/en/concept/permitted-margin-for-deviations/)
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/tolerance-prince2/

## Definition

Tolerance in PRINCE2 is the permitted margin around a planned target, such as a budget or a date. Within this margin the responsible level may act on its own; only when the forecast threatens to leave it does the level above have to be involved. Tolerances are set for various aspects, for example time, cost, scope, quality, benefits and risk. They are delegated in steps: by the commissioning organization for the project, by the Project Board for stages and by the Project Manager for work packages. Tolerances are therefore the tool through which management by exception is put into practice.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Variance threshold](https://pmdecoder.com/en/glossary/variance-threshold/) | equivalent | — |

## Distinction

The variance threshold in ISO 21506 describes the same idea of a defined limit. Risk tolerance, by contrast, refers only to the willingness to take risks. A variance is the actual difference between plan and actual; tolerance determines how large a variance may be before it must be escalated. A reserve or buffer is planned time or money, not a decision limit.

## In practice

For the fit-out stage of an office refurbishment, the Project Board sets a budget of 1.2 million euros with plus ten and minus five per cent and a completion date with three weeks of leeway. No scope tolerance is given: all agreed rooms must be finished. The Project Manager handles a seven per cent cost increase himself.

## Frequently asked questions

### Can a tolerance be zero?

Yes. It means that any deviation in that aspect must be referred to the Project Board, for example when a statutory deadline cannot be moved.

### Why is there a tolerance below the target as well?

Because significantly lower costs or much earlier completion can also point to planning errors or missing scope. The level above should be made aware of this.

## Related terms

- [Variance threshold](https://pmdecoder.com/en/glossary/variance-threshold/)
- [Risk tolerance](https://pmdecoder.com/en/glossary/risk-tolerance/)
- [Manage by exception principle](https://pmdecoder.com/en/glossary/manage-by-exception-principle/)
- [Exception (PRINCE2)](https://pmdecoder.com/en/glossary/exception-prince2/)
- [Variance](https://pmdecoder.com/en/glossary/variance/)
- [Exception Report](https://pmdecoder.com/en/glossary/exception-report/)
- [Exception Plan](https://pmdecoder.com/en/glossary/exception-plan/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.