# Timebox

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Working in fixed time frames](https://pmdecoder.com/en/concept/working-in-fixed-time-frames/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/timebox/

## Definition

In PMI usage a timebox is a brief, fixed span of time within which work must be finished. The length is set in advance and is not extended; whatever cannot be done within the time is reassessed instead of moving the deadline. Scope is thus flexible, not time. Timeboxes come in different sizes: a two-week iteration is a timebox, as is a coordination meeting limited to fifteen minutes or half a day for a technical investigation. The fixed limit forces prioritization, makes progress visible at regular intervals and prevents work from continuing endlessly without a result.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Timeboxing](https://pmdecoder.com/en/glossary/timeboxing/) | closely related | denotes the fixed time period itself, timeboxing the working with it |

## Distinction

The cross-framework term timeboxing denotes the way of working, the timebox the individual limited period; the relationship is therefore close but not equivalent. An iteration is a specific timebox for a development cycle. A date in a traditional schedule, by contrast, fixes the scope and lets the date slip when there are delays.

## In practice

A team is unsure whether a mapping library is suitable for its application. It agrees on a timebox of two working days for a technical test. When the time is up it presents the result, even if not all questions are answered, and then decides whether to invest more time or choose another solution.

## Frequently asked questions

### What happens when the timebox expires and the work is not finished?

The work stops and is assessed. The team decides whether the remainder goes into a new timebox, is reduced or is dropped. The deadline itself is not moved.

### Why are timeboxes usually short?

Short periods allow frequent feedback and limit the damage if a direction turns out to be wrong.

## Related terms

- [Timeboxing](https://pmdecoder.com/en/glossary/timeboxing/)
- [Iteration](https://pmdecoder.com/en/glossary/iteration-pmi/)
- [Sprint](https://pmdecoder.com/en/glossary/sprint/)
- [Burndown chart](https://pmdecoder.com/en/glossary/burndown-chart/)
- [Daily Scrum](https://pmdecoder.com/en/glossary/daily-scrum/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.