# Time-phased budget

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.91
- Edition: ISO 21506:2024
- Topic area: [Monitoring and control](https://pmdecoder.com/en/area/monitoring-and-control/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/time-phased-budget/

## Definition

A total budget on its own does not say when money will be needed. A time-phased budget therefore specifies which share falls in which month, quarter or phase, in line with the schedule of the work packages. Accumulated over time, this produces a curve that is typically S-shaped. It is the basis for planned value in earned value management and for cash planning.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Planned value is the figure that the time-phased budget yields for a particular cut-off date. The performance measurement baseline is the time-phased budget of the entire project without the management reserve. A cash outflow plan, by contrast, describes when payments fall due, which can differ considerably from when the work is actually performed.

## In practice

A university plans to refurbish a lecture hall building over 18 months for 6 million euros. Instead of spreading the budget evenly across the months, the building department follows the schedule: planning and strip-out work account for 400,000 euros in the first three months, and the main trades for 3.6 million euros in months seven to twelve. Only in this way does a comparison with actual progress in month four give a realistic picture.

## Frequently asked questions

### Why is an even distribution not good enough?

Because projects rarely incur costs evenly. With a linear distribution, a project would appear to be behind at the start and ahead later on.

### How finely is the budget distributed?

Usually by reporting period, that is monthly or every four weeks. For later stages a coarser distribution is often sufficient, refined step by step with rolling wave planning.

## Related terms

- [Planned value](https://pmdecoder.com/en/glossary/planned-value/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline/)
- [Cost planning](https://pmdecoder.com/en/glossary/cost-planning/)
- [Rolling wave planning](https://pmdecoder.com/en/glossary/rolling-wave-planning/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.