# Time and materials contract

abbr. T&M contract

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Contract billed by effort](https://pmdecoder.com/en/concept/contract-billed-by-effort/)
- Topic area: [Contracts and procurement](https://pmdecoder.com/en/area/contracts-and-procurement/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/time-and-materials-contract/

## Definition

Under a time and materials contract, the client pays for the hours or days actually worked at fixed rates per qualification, plus the materials used, often with a mark-up. The scope of work may be open or only roughly described. To limit the cost risk, ceilings, quotas of hours or regular approvals are often agreed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Time and materials contract](https://pmdecoder.com/en/glossary/time-and-materials-contract-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Contract](https://pmdecoder.com/en/glossary/contract/)

## Distinction

A fixed-price contract sets a total price for a defined scope; a time and materials contract sets only prices per unit. It differs from a cost-reimbursable contract in that no actual costs are disclosed; agreed rates are charged instead. In Germany, such an agreement is often structured as a contract for services (Dienstvertrag), but it can also contain elements of a contract for work (Werkvertrag).

## In practice

An insurer brings in an external development team to enhance its customer app. Because requirements are reprioritized in short cycles, both sides agree to bill according to effort, with daily rates and a ceiling per quarter. Every other week, the team presents results and the days used. When seventy per cent of the quarterly budget has been used up, the insurer decides which features will still be implemented.

## Frequently asked questions

### Who bears the risk under a time and materials contract?

Mainly the client, because it pays for every additional effort. The contractor mainly bears the risk of providing suitable staff.

### What should be watched when billing?

Traceable activity records, clear rules for travel time and material mark-ups, and agreed approvals before quotas are exceeded.

## Related terms

- [Fixed-price contract](https://pmdecoder.com/en/glossary/fixed-price-contract/)
- [Cost-reimbursable contract](https://pmdecoder.com/en/glossary/cost-reimbursable-contract/)
- [Agile project management](https://pmdecoder.com/en/glossary/agile-project-management/)

---